SpaceX is betting $74 billion on AI data centers. Texas and Arizona want to know who pays
SpaceX wants to build a data center in the Arizona desert that would consume 6,000 megawatts of power at full capacity. That’s nearly two-thirds of the historic peak demand that the Arizona utility, which serves about 1.5 million homes and businesses, achieved this summer across its system, according to KJZZ.
The Cochise County campus makes up the largest part of a plan SpaceX announced Nov. 12 to spend more than $74 billion on two AI supercomputing sites: about $50 billion in southeastern Arizona and more than $24 billion at Starbase, Texas, Reuters reported. The company touts both as profitable projects, with on-site electricity in Texas, dry cooling in Arizona and promises of lower bills and taxes for neighbors.
Residents, local officials and now Arizona’s attorney general want proof first. Who bears the cost of the power plants, water and grid upgrades behind AI, the company or the people who live next door, is quickly becoming the question that decides whether these campuses will be built.
The stakes for SpaceX are high. Its AI segment generated more than half of its revenue in the third quarter, ahead of rockets and Starlink, according to Reuters, and Fortune explained how leasing IT capacity to Anthropic and Google has become central to the company’s valuation. The political terrain is also shifting in the sector: Voters came out against data center development in 37 of the 38 fully counted local elections this month, as shown Fortune reported after the midterms.
In Texas, a land swap puts the project out of moratorium
The Texas campus is a gas-fired power plant and “supercomputing facility” located on 444.45 acres near the Brownsville Port, The Texas Tribune reported. Brownsville deannexed the land earlier this year at the request of SpaceX, after the company offered $220 million for water and wastewater projects in the city. The neighboring town of Starbase, which formed around the SpaceX launch site in 2025, later annexed it.
That sequence leaves the project outside the reach of Brownsville’s 90-day data center moratorium, which went into effect in early November. The city says its decision was based on “the information and circumstances presented at the time.”
Because the plant would produce its own electricity, SpaceX says the facility will not be powered by the public grid. This will still burn a lot of gas. The Texas Commission on Environmental Quality issued an air permit Nov. 16 authorizing the construction of 35 natural gas turbines producing 750 megawatts and up to 248 tons of nitrogen oxides per year. News week reported, citing Policy.
The South Texas Environmental Justice Network announced a protest, arguing the facilities would pollute the air, consume water and increase residents’ energy bills. Other residents see an opportunity. “A lot of people need jobs in our community and SpaceX has helped make those jobs happen,” said Janie Melendez, a Brownsville teacher who previously served on the executive committee of the Republican Party of Texas. Tribune.
Melendez felt the pull of SpaceX in another way. “Since SpaceX moved in, the value of my house has tripled,” she said. Rising values are a win for homeowners, but they tend to increase property tax bills and rents, which can crush new residents and renters.
The tax issue is now topical. On Nov. 17, Cameron County commissioners voted 3-2 against continuing negotiations on a 100 percent property tax abatement over 10 years for the project. Starbase’s own city commission is expected to consider a tax cut on Dec. 9. And in January, SpaceX will face a new governor, Gina Hinojosa, who has pledged to freeze data center approvals until lawmakers pass new protections.
In Arizona, a 6 gigawatt campus tests a rural network
The Arizona campus would span 747 acres near Willcox Playa, about 80 miles east of Tucson, according to the Arizona Daily Star. It would take power from the grid through Sulfur Springs Valley Electric Cooperative and Arizona Electric Power Cooperative, and SpaceX says the nearby Apache Power Plant, which burns coal and natural gas, would go from about 1 gigawatt to more than 6 gigawatts. The permit application lists $3.6 billion in planned network upgrades.
SpaceX’s pitch to the county is aggressive. At a community meeting, Riley Trettle, who heads SpaceX’s energy and supercomputers department, said the project would lower residents’ electricity bills, reduce property taxes by 20% and create about 1,000 permanent jobs, according to the Star. The application projects a one-time sales tax benefit of $250 million to the county and $35 million to $103 million in sales tax revenue, and the company expects about 5,500 construction jobs.
Water is the most acute concern. The campus would be dry cooled and would not pump groundwater for industrial purposes, although an existing well could provide up to 10 acre-feet per year for drinking water and maintenance. Residents point to an aquifer already depleted by large dairy farms, and experts told the Star that water used to generate campus electricity could increase annual data center water consumption by 60 to 90 percent. The permit does not estimate this figure.
On Nov. 19, Attorney General Kris Mayes asked the Cochise County Planning and Zoning Commission to postpone its Dec. 9 vote until state and federal agencies can review the project. His letter questions how SpaceX would cover energy needs beyond what the regional cooperative can generate, and raises concerns about water, fire safety, traffic, wildlife and proximity to Fort Huachuca. “The residents of Cochise County deserve answers before county officials approve a project of this magnitude,” Mayes said in a statement. She is planning her own town hall at Cochise Elementary School on Dec. 3.
Does growth pay for growth?
Arizona’s largest utilities are already struggling with the same distribution of costs. APS describes its approach as “growth pays for growth”: Large customers sign long-term contracts so that they, rather than residential and small commercial customers, cover the infrastructure they need, Scripps News reported. Data centers accounted for about 7% of APS’ peak load this year, up from about 5% last year, according to KJZZ.
Regulators draw a finer line. Arizona Corporation Commissioner Kevin Thompson says data centers will pay for any new generation they need, but all customers should share in reliability investments that benefit the entire network. “If it’s for the good of the grill as a whole, then that peanut butter should be spread on the bread, right?” he told KJZZ.
Meanwhile, APS is asking the commission to approve a 14 to 16 percent rate increase for residential customers. In that case, an APS witness, Jamie Moe, agreed that residential demand did not come with high costs associated with growth, KJZZ reported.
SpaceX’s Arizona campus would be served by cooperatives rather than APS, but any rate increase would still require approval from the Corporation Commission. The Dec. 9 votes at Starbase and Cochise County will be the first public tests of whether SpaceX’s promise that its AI campuses will pay for themselves will hold once the bills and gigawatts come due.
Gn bussni